Based on the City Manager's Memos
...as misconstrued by Ron.
- At the Health & Wellness Center:
- Framing continues at the Teen Center and kitchen area.
- Electrical wiring continues at the Activity Center and Teen Center.
- Pool excavation is complete; plumbing and piping work has begun.
- HVAC and mechanical rough installation has begun.
- Activity Center foundation has been poured.
- Slab pour completed at Activity Center.
- On-site utility trenching has commenced.
- Trusses have been loaded at the Activity Center and in area south of Kitchen.
- Plywood siding is being installed at the Teen Center.
- Steel beams for the gym were delivered and will be installed on January 23rd.
- Assembling easement and bill of sale documents for electrical and communication service to the complex.
- Working to close the New Market Tax Credits. Secured the first $2 Million.